Commission awards Terra Valley lift‑station decommissioning bid to Crow River Construction
Summary
The commission awarded a roughly $1,000,000 contract to Crow River Construction to decommission the Terra Valley lift station, replace a force main with a gravity sewer and tie into the Sunrise View lift station; bids came in about 10% under the $1.1 million estimate.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
City engineering staff summarized the Terra Valley decommissioning project on Jan. 6 and asked the commission to award the construction contract. The project replaces an existing lift station and force main with a gravity sewer alignment that ties into a new lift station in the Sunrise View development.
Riley, representing engineering staff, said the project was estimated at $1.1 million and that bids came in roughly 10% under estimate; Crow River Construction submitted the apparent low bid at approximately $1,000,000. Riley confirmed the work is open‑trench and fully underground, with restoration following trenching.
After brief commissioner Q&A about construction methods, the commission voted to award the contract to Crow River Construction.