Village manager outlines pedestrian, sewer and parks projects and budget timeline
Summary
Village Manager Kyle Henkelman briefed council on infrastructure projects: SR-571 pedestrian improvements (on schedule, expected by end of September), a 3,200-foot trunk sewer replacement (15 manholes), Village Service Center renovations, Founders Park survey and early site work, and the budget timeline leading to an adoption target in December.
Get email alerts on the Infrastructure And Budget topic
No spam. Unsubscribe anytime.
Village Manager Kyle Henkelman used the council meeting to summarize several ongoing and planned projects and the budget timetable.
Henkelman said the State Route 571 Pedestrian Improvement Project (an expanded pedestrian path for walkers and bicyclists) is on schedule and on budget, with a target to complete the work by the end of September. He described a sanitary sewer trunk main replacement running about 3,200 feet from the wastewater treatment plant north and replacement of roughly 15 manholes; staff said alignment work began this week and reclamation should follow, with completion expected before the end of the year.
Henkelman said the village is also reviewing a Haskett and Hamilton roadway improvement project likely to move forward in 2027, and that renovations at the Village Service Center began the prior Monday with an expected completion before winter. He said the village is working on a project page for each major project so the public can track timelines and budgets.
On Stillwater Crossing, Henkelman said he is trying to schedule a meeting with the developer for an update; council members raised concerns about high grass and weeds on the site and asked staff to request developer attention to those maintenance issues. Service Director Ben Herron told the council a survey is underway for Founders Park because property pins could not be located; crews plan to install gravel for an interim parking area and schedule contractors for fencing and a shade structure.
Henkelman also outlined a changed budget process aimed at more narrative explanation. He said department heads will meet in late July and early August to prepare materials, the finance committee (three council members and department heads) will meet in August, and the goal is to present a draft for council discussion in September and adopt the budget in December.
What happens next: Staff will continue project coordination and return monthly with updates; the village manager will prepare budget materials in time for finance committee review and the council's fall budget schedule.