Pulaski engineering overview: water, sewer and transportation projects total tens of millions; filter plant a $25 million priority

Pulaski Town Council · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town engineer Austin Painter told council the town's capital-improvement pipeline includes $27.43 million in water projects (including a $25 million filter plant upgrade), roughly $6.5 million in sewer work (including the interceptor), and about $17 million in transportation projects; several projects are awaiting funding or design steps.

Austin Painter, the town engineer, gave an overview of ongoing and proposed capital-improvement projects and recurring engineering task items.

Painter said water projects total approximately $27,430,000 overall with nearly $25,000,000 associated with a raw water pump station and filter-plant rehabilitation; he said about $3,000,000 in grants and just under $1,000,000 in loans are already allocated for portions of the work. The lead service line program remains active, with 333 service-line connections yet to be documented under the Virginia Department of Health’s statistical-identification approach.

On sewer, Painter listed roughly $6.5 million in projects, the largest being the Pulaski interceptor rehabilitation (discussed separately by CHA). He said an infiltration-and-inflow abatement project is on hold pending funding and another recent grant funded a sewer pump-station preliminary engineering report.

Transportations projects number eight for a combined total near $17 million, including three bridge projects and a streetscape effort that is in finalization steps; Painter said one bridge bid came back higher than estimates and is being reworked. Painter also noted environmental work: floodplain acquisition efforts and Army Corps work on a low-head dam that has been paused after soil tests.

Painter closed by highlighting general-property projects (basement flood remediation and a cemetery GIS digitization project), noting the latter is in finalization and will unify burial records into the town GIS.

Council members asked follow-up questions about PCB testing (which Painter said has come back lower than initial expectations, with exact numbers not specified) and business-owner feedback on streetscape part 2 (mixed views). Painter offered to follow up with specifics as requested.