Whitnall reviews options to connect Edgerton Elementary to S. 116th Street water main; village permits required

Whitnall School District Board of Education · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent told the Whitnall board the district prefers to tap the water main in S. 116th Street to serve Edgerton Elementary but must secure a right‑of‑way permit; an off‑Edgerton alternative would likely add roughly $200,000 in taxpayer cost, and village approvals tied to grant funding must be cleared before late July.

The Whitnall School District superintendent updated the board on efforts to secure a right‑of‑way permit to connect Edgerton Elementary School to a water main located in the middle of S. 116th Street.

The superintendent outlined two primary technical approaches: trenching a roughly 5‑foot trench to drill into the S. 116th Street water main, then backfilling and using infrared paving to minimize surface disruption; or, as a fallback, performing a larger repaving section funded in part from contingency. The superintendent said trenching into S. 116th is preferred.

A less desirable alternative — routing the connection off Edgerton — would require additional engineering and is estimated in the meeting to raise local taxpayer costs by about $200,000, the superintendent said. The superintendent described legal and grant‑funding technicalities with the village’s prior road project that require coordination; village staff and contractors have been engaged in discussions and the superintendent said he expects a solution by the end of July if approvals proceed.

Board members asked which agency issues the right‑of‑way permit; the superintendent said the Hales Corners Department of Public Works handles the permit. The superintendent advised the board that no board action was required at this meeting but that staff will return with updates if problems arise.

Next steps: staff will continue coordination with the village, contractors and any funders to resolve permitting details before school opens.