Board directs staff to pursue design‑build process for new high school after presentation
Summary
After a presentation on delivery methods and guarantees, the board voted to pursue a design‑build procurement for the proposed new Martin County high school and asked staff to prepare an RFQ, noting contract provisions to protect against opening with major defects.
Get email alerts on the High School Construction topic
No spam. Unsubscribe anytime.
Mister McPherson presented construction delivery options for a proposed new Martin County high school and answered board questions about guaranteed maximum price (GMP), construction manager roles and warranty protections.
"When we talk about that, we're talking about the guaranteed maximum price that is provided by the building contractor ... it is set as a do not exceed price," McPherson said, explaining that GMPs are assembled from subcontractor bids and can change with change orders or changes in conditions.
McPherson urged contract language and procurement choices that protect the district from major defects at opening: "A roofing mechanism should not be leaking on your first day in operation. You should not be getting a ... certificate of occupancy with that many leaks," he said, and recommended including specific roofing provisions and warranty terms.
Following questions and discussion, Burgess moved that the board go with the design‑build delivery method; the motion was seconded and approved by voice vote. McPherson said he will work with Dr. White to prepare a request for qualifications (RFQ) for a design‑build team.
The board’s direction is procedural: it does not award a construction contract but authorizes staff to pursue procurement steps for the design‑build method and to develop RFQ documentation and contract provisions to reflect the protections discussed.