Mebane awards engineering contract for FEMA BRIC sewer rehab; project budget approved
Summary
Council awarded a phase‑1 engineering contract for the Bridal sewer rehabilitation project tied to FEMA BRIC funding, accepted a $198,750 BRIC grant for engineering and approved a capital project ordinance to move the project forward.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The City of Mebane approved awarding the phase‑1 engineering contract for the Bridal sewer rehabilitation project as part of a FEMA BRIC grant on Dec. 2.
Staff said the city will receive roughly $198,750 from FEMA BRIC for phase‑1 engineering, requiring a local match; the full project budget was presented as roughly $3.0 million, including engineering and construction. The city received a single responsive qualification package and staff recommended awarding the phase‑1 engineering contract to the respondent. Council voted to award the contract and approved the capital project ordinance to proceed into engineering and later construction phases.