Committee member requests sewer televising ahead of MnDOT Highway 60 repaving

Kenyon City Council · July 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A committee member requested the city approve televising sanitary sewer on Highway 60 before MnDOT repaves the roadway, citing possible utility needs that could require full reconstruction and shared costs; Bijou Sewer submitted the low quote and the work would show mains and service connections but not full service‑line interiors.

A committee member asked Kenyon officials to accept bids to televise the sanitary sewer on Highway 60 ahead of planned Minnesota Department of Transportation repaving, saying the results could determine whether the city requests MnDOT to include utility reconstruction during the road project.

The member said three quotes were in the meeting packet and that Bijou Sewer submitted the low bid; Bijou’s pricing may be favorable because the company is also doing sewer lining for the city's 2025 Scribe project. The televising would allow inspection of the sewer main and the connection from service lines to the main but would not permit full internal inspection of individual service lines.

"If we tell MnDOT we have significant utility needs and we need to go after the water main and sewer, that means we're digging up the entire width of the roadway... That becomes an entirely different type of project, an entirely different cost category," the committee member said, warning that substantial findings could require the city to participate in a reconstruction project with MnDOT.

The member said the televising cost per service could be "like, $500 to $1,000 per service," and noted the expense was accounted for in the public works budget; the item on the agenda requested authorization to proceed with the quotes in the packet so the city can make an informed decision ahead of MnDOT work next year. The transcript does not record a formal vote or final decision on the televising request.

Separately, the member gave a brief status update on the 2025 Street Utility project: crews may be in town as soon as tomorrow, with sewer line work starting next week; final paving is outstanding, with final completion expected in mid‑July and a punch‑list deadline around Aug. 30.