Town approves securities, agreements for Gardner Ridge project in Gardnertown
Summary
The board approved multiple securities and agreements required by the Planning Board for the Gardner Ridge development in Gardnertown, including off-site roadway work ($168,989 estimate), stormwater securities ($845,159.50), landscape and tree-protection securities, and a stormwater control agreement; one councilmember abstained on several approvals.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Town Board approved a suite of actions required for conditional final approval of the Gardner Ridge development in Gardnertown, including off-site roadway improvements, stormwater erosion and sediment-control securities, landscape security and inspection fees, a stormwater control agreement, and tree-protection securities.
Patrick J. Hines, the town engineer, said the Planning Board’s conditional approval requires posting securities for reconstruction of portions of Gardnertown Road/Creek Run Road. The applicant’s engineer estimated the off-site roadway cost at $168,989.00; a 4% inspection fee equates to about $1,760.00. The board approved the off-site roadway improvements.
Hines also presented the engineer’s probable-construction-cost estimate for required stormwater erosion and sediment-control securities totaling $845,159.50 and a 4% inspection fee of $33,806.00. The board approved the stormwater securities; the minutes record Councilmember Mary Lou Carolan abstained while other members voted yes.
The board approved landscape security and noted a required landscape inspection fee of $4,000 that must be posted before the Planning Board will stamp plans. The stormwater control agreement was approved; the town attorney presented a Declaration of Restriction and advised no vote was required to acknowledge review, which the board recorded.
Finally, the engineer calculated tree-protection securities under Town Code Chapter 172 totaling $18,481.25 and a tree-inspection escrow of $1,000; the board approved posting these securities. The approvals signal the board’s concurrence with the Planning Board conditions; the minutes do not record negotiated changes to the engineering estimates or an updated final construction schedule.