Engineers recommend smaller covered fishing pier and possible site upgrades for deteriorated Whimbey Creek pier; county to target ~$2M for combined improvements
Summary
An alternatives analysis found the derelict Windy (Whimbey) Creek fishing pier is close to collapse; engineers recommended rebuilding a smaller fixed covered pier with upgraded materials (estimated $1.1–1.3M) and presented a hybrid option combining pier replacement with boat‑landing and parking improvements that could cost around $2M; staff will bring funding proposals for A&H tax or CIP consideration.
Get email alerts on the Pier Rehabilitation topic
No spam. Unsubscribe anytime.
Engineers presented an alternatives analysis to Beaufort County's Public Facilities and Safety Committee on Nov. 18 for the Whimbey (Windy) Creek Fishing Pier, a former railroad trestle partially collapsed after a fire.
The pier was rated poor to serious in a 2019 inspection and is in critical condition now because of fire damage and foundation failure, the engineer said. The county considered multiple options: doing nothing (not recommended because of liability); demolishing the pier and not replacing it; rebuilding the full existing pier with timber (lower cost, lower longevity) or upgraded materials (higher durability); or building a smaller fixed covered pier with a gangway down to a floating dock for fishing and crabbing.
Engineers recommended a smaller covered fixed pier using upgraded materials (aluminum, fiber‑reinforced polymer, concrete or steel) with a smaller floating dock; that configuration was estimated at roughly $1.1–$1.3 million inclusive of demolition. Staff also presented a hybrid option combining the preferred pier rebuild with site work to expand parking and improve the adjacent boat landing, which could approach $2 million depending on site‑work scope. Staff noted the larger hybrid option could be phased and that any project will need design and permitting (estimated one year for design/permitting and six months for construction once funded).
Committee members favored a combined approach to both remove the dangerous structure and provide improved access and parking; they requested staff return with refined cost estimates and a proposed funding source. Staff suggested A&H (Accommodations & Hospitality) tax funds as an appropriate source and said a small CIP/A&H package would be proposed to finance some county projects.
What happens next: Staff will refine a recommended option (combination of D1 and E0.1 in the analysis), prepare detailed designs and cost estimates, and include the project in an A&H tax mini‑CIP proposal coming to finance committee in the next week for broader funding discussion.