Belmont seeks engineering oversight for Route 140 WRBP task order; board approves $10,000 retention
Summary
Selectmen reviewed a Route 140 task order and raised concerns about language that prevents town review until 90% design. The board voted to retain retained engineer Underwood for kickoff and 30/60/90 review points, approving a proposed $10,000 advisory contract to preserve the town's input during the design-bid process.
Get email alerts on the Infrastructure Project topic
No spam. Unsubscribe anytime.
Staff member (S1) told the board the design task order for the Route 140 WRBP project contained a clause that would prevent meaningful town review until the design reached 90 percent completion. That language raised concern among selectmen and the advisory board and prompted a recommendation to require 30/60/90 review milestones.
"If I'm looking at this, they're saying that nobody can look at their design until it's 90%..." a selectman said, noting the town historically asks for 30/60/90 checkpoints.
Underwood, the town's retained engineering advisor for the project, will be asked to provide advice and attend kickoff and design-review meetings to ensure the town's voice is represented during design and task-order reviews. The board discussed retaining Underwood for a small advisory contract (S1 suggested $10,000) to attend kickoff, review task orders and offer timely comments.
A motion to retain Underwood for kickoff and design-review oversight passed by voice vote. Board members said the $10,000 advisory contract on a project with multi-million-dollar construction phases was a reasonable expense to avoid being locked out of critical design decisions and to mitigate the risk of large future cost overruns.
Members emphasized that the retention covered design-phase advisory services, not construction inspection or on-site engineering, and asked staff to request a written scope from Underwood specifying deliverables and the 30/60/90 review schedule.