Utility board outlines sewer work and financing as council presses for clearer cost breakdown

Charles Town City Council · August 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council heard a multi-part utility presentation that placed the collection-system construction estimate at about $5.3 million and the total program at roughly $6.6 million with soft costs; council members pressed staff for a line-by-line breakdown, and public commenters asked why capacity-improvement fees fell from earlier estimates.

Charles Town — The city’s utility board told council members on Aug. 5 that a multi-year sewer-replacement program will be carried forward to bid this fall after the board completed value-engineering work on the most expensive pump-station component.

On a packed agenda, Miss Dawson, the utility board representative who spoke to council, said the board’s renewal-and-replacement contract for the wastewater plant is a $10.8 million construction program and that the collection-system component now carries a construction estimate of $5,300,000 and total project soft costs that bring the combined project-level total to about $6,600,000.

“Current engineer’s estimate of construction is $5,300,000,” Miss Dawson said during the board briefing, and she described a strategy to put a pricey Flowing Springs pump station into the contract as an add-alternate after redesign and value engineering reduced its scope and estimated cost.

Public commenter Jackie Miller urged the council to publish a side-by-side ledger of the project’s costs over time. “Back in January this council saw an original $4,800,000 project,” Miller said in public comment, adding that earlier public materials had shown capacity-improvement-fee contributions near $1,300,000 but later figures that she read as roughly $910,000. Miller asked whether contingency and soft costs were included in the lower figures and where the reductions came from.

Council members asked several technical and budgetary questions: what the total program price tag would be with engineering and legal soft costs included (Miss Dawson estimated roughly $12 million for the renewal-and-replacement package, including soft costs), how grant proceeds and SRF loans are being applied, and whether removing the Flowing Springs pump-station work from the base bid would materially change what ratepayers must fund.

Miss Dawson described available funding sources: a favorable Clean Water State Revolving Fund (SRF) loan of roughly $2.85 million, a $500,000 green-infrastructure grant, and a $1.6 million EEG grant that could be applied if construction begins in time to meet grant deadlines. She said those awards, together with internal renewal-and-replacement funds and capacity-improvement fees, shape the final local share.

On how much of the project is growth-driven, Miss Dawson said the board’s accounting shows roughly a 55% growth-related share and a 45% non-growth share across the project components; that allocation is used to calculate the capacity-improvement-fee portion of the local match.

Council members pressed staff to publish a component-level reconciliation of the figures that shows what changed since earlier project materials. “We went from $4.8 million to $6.6 million while pulling roughly $3.0 million of that pump-station scope out,” one council member said, asking for a line-item breakdown of construction, contingency and soft costs so the council and public could see exactly where increases occurred.

Miss Dawson also updated the council on compliance and planning items: the board is nearing completion of a lead-and-copper inventory required by federal rules, has nearly obtained all easements for the collection-system project, and anticipates advertising the collection-system bid in September with construction to start in December to meet grant deadlines.

The council did not take a final vote on a project ordinance revision during the meeting but directed staff to return with the detailed cost breakdown, grant-by-grant accounting, and the plan for how the Flowing Springs pump station will be packaged as an add-alternate for bidders.

The utility board plans a community tour once construction of the wastewater plant renewal project reaches substantial completion; staff said substantial completion is anticipated in November.