Wakefield Permanent Building Committee approves multiple vendor invoices and change orders; staff flags technology overrun
Summary
The Wakefield Permanent Building Committee approved several vendor invoices and change orders, including a $116,381.37 change order from soft-cost contingency and a not-to-exceed $266,654 lighting purchase for Burnett Field. Staff disclosed a miscount that left 49 short-throw projectors out of the bid, pushing the technology budget over its planned line.
Get email alerts on the Project Budgeting topic
No spam. Unsubscribe anytime.
The Wakefield Permanent Building Committee on Tuesday approved a series of vendor invoices and change orders and was notified that the project’s technology budget is over its previously set line after a miscount in the bid documents.
Committee members voted to approve invoices that included a Left Field invoice (invoice #195348) for $145,000 and an SMMA invoice for $114,937.23. The committee also approved a utility-related invoice submitted by WMGLD/WMTLD for the creation of service lines and hookups. Motions on these items passed by unanimous voice votes.
Staff told the committee that a miscount in the bid documents left 40 projectors specified while 89 classrooms need short-throw projectors, leaving 49 additional units unbidded. In describing the error, a project staff member said, “there’s just no 2 ways about it. It was a mess.” The staff member who presented the budget said a purchase order and change order are being processed now and that a final reconciliation of the technology budget will be returned to the committee next month.
The committee approved change order number 2 as a purchase order not to exceed $116,381.37, with the understanding that the owner’s soft-cost contingency would be used if required. A separate contingency transfer of $38,254 was approved and characterized in the presentation as producing a $0 net change to the project overall.
On site improvements, the committee approved lighting for Burnett Field — described in the meeting as the Moscow field lighting installation package — with a not-to-exceed price of $266,654 to come from construction contingency after staff reported the estimate had declined by about $20,000 since an earlier estimate.
Project finance staff gave a status snapshot: as of June, the project had committed about 92% of its budget and expended roughly 68%, with an uncommitted balance noted at $21,343,370 and construction at approximately 71% complete. The staff presenter said those figures would be refined once the technology reconciliation and other outstanding items settle.
Committee members asked procedural questions about future budget revisions; staff explained that any material change to the technology budget would require a formal budget revision request to move funds from the owner soft-cost contingency into the technology line.
Next steps: staff will return with a detailed technology-budget reconciliation and final change-order amounts at the committee’s next meeting. The committee also reminded members of an August 6 site tour and upcoming working-group meetings.