Council approves Thompson Litton agreement to replace flood-damaged wastewater clarifier; FEMA to reimburse most costs

Narrows Town Council · January 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a Thompson Litton project agreement to replace a primary clarifier damaged by flooding; staff said FEMA will reimburse about 92% of the repair costs and the town may use bridge loan funds for up-front payments.

The Narrows Town Council voted on Jan. 12 to accept a project agreement with Thompson Litton to replace a flood-damaged primary clarifier at the town wastewater treatment plant.

Staff said the work is reimbursable by FEMA at approximately 92% and that the town may need to tap previously approved bridge loan funds to cover the remainder and up-front expenses. "That 100%. It will be the, the 92%," a staff member said when describing expected FEMA reimbursement.

The town attorney (or staff counsel) recommended a minor correction to the agreement's numbering and asked that the scope explicitly include preparation of EJCDC contract documents for the construction contract; councilors moved to accept the agreement with those edits and to authorize the manager to sign.

The motion carried on a roll-call vote.

What's next: Staff will finalize the project agreement with the requested edits, proceed with the bid package and submit required documentation for FEMA reimbursement.