Council approves library HVAC and Horeb Springs retaining‑wall bids; retaining wall comes in over budget

Waukesha City Common Council · July 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council accepted Lee Mechanical’s $394,621 low bid for library HVAC improvements and Always Contractors’ $488,906 low bid for the Horeb Springs retaining wall. Council discussed that the retaining-wall project came in well over the original $185,000 budget due to inflation and slight scope increases; the library bid passed unanimously and the retaining‑wall bid passed 12–1.

Board of Public Works staff presented two bids: the low base bid for the library HVAC improvement project from Lee Mechanical for $394,621, and the low base bid for the Horeb Springs retaining wall from Always Contractors for $488,906.

Council members asked about the large variance between the retaining-wall budget (listed at about $185,000) and the low bid; staff said the budget figure dated from 2021 and that inflation—especially for concrete—and a small scope increase (an added wing wall) pushed the low bid higher. Staff said the Park & Rec department and finance staff identified carryover funds to cover the difference.

Council approved the library HVAC bid by unanimous vote and approved the Horeb Springs retaining-wall contract (motion recorded as passing 12–1). Staff noted the retaining-wall estimate represents roughly a 10–15% increase in square footage from earlier scope estimates and that the budget should be updated to reflect more current estimates in future capital planning.