Waukesha utility presents operations-center cost update; PSC allowance leaves contingency space

Waukesha City Water Utility Commission · July 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Utility staff updated commissioners on the operations-center construction: projected costs shown at about $22.8 million vs. a PSC-approved allowance of $25.3 million, and staff flagged several long-lead items (fiber, network switches) and one-time city impact fees that will require tracking and future change orders.

Utility staff presented a progress and budget update for the new operations center, showing a projected total near $22.8 million compared with a Public Service Commission allowance of $25.3 million.

Kelly outlined what is approved versus estimated: $750,000 is in place for architecture and engineering; furniture, AV, and some network components remain estimates; fiber to the site is estimated at about $59,000 and a city impact fee was listed at $10,277.13 (a one-time fee payable before the building permit). Staff said network switches procured from city IT have long lead times and are estimated at roughly $152,000. To avoid halting construction, staff proposed using the work change directive process for interim approvals and returning with formal change orders.

Commissioners asked to see clearer budget-versus-actual comparisons and requested slides with larger text or a two-page layout that shows alternatives and variances. Staff agreed to provide a more detailed, reader-friendly presentation showing the budgeted amount and projected costs and to return with formal contract amendments for significant items. Staff said manufacturing of some equipment is already underway and Earth-moving could begin once the building permit is issued.