Waukesha utility presents operations-center cost update; PSC allowance leaves contingency space
Summary
Utility staff updated commissioners on the operations-center construction: projected costs shown at about $22.8 million vs. a PSC-approved allowance of $25.3 million, and staff flagged several long-lead items (fiber, network switches) and one-time city impact fees that will require tracking and future change orders.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Utility staff presented a progress and budget update for the new operations center, showing a projected total near $22.8 million compared with a Public Service Commission allowance of $25.3 million.
Kelly outlined what is approved versus estimated: $750,000 is in place for architecture and engineering; furniture, AV, and some network components remain estimates; fiber to the site is estimated at about $59,000 and a city impact fee was listed at $10,277.13 (a one-time fee payable before the building permit). Staff said network switches procured from city IT have long lead times and are estimated at roughly $152,000. To avoid halting construction, staff proposed using the work change directive process for interim approvals and returning with formal change orders.
Commissioners asked to see clearer budget-versus-actual comparisons and requested slides with larger text or a two-page layout that shows alternatives and variances. Staff agreed to provide a more detailed, reader-friendly presentation showing the budgeted amount and projected costs and to return with formal contract amendments for significant items. Staff said manufacturing of some equipment is already underway and Earth-moving could begin once the building permit is issued.