City to replace exposed Fresno River water main; lowest responsive bid at roughly $307,000 approved
Summary
Assistant Engineer Gomez said the city received four bids to replace about 227 linear feet of water transmission main exposed by riverbed erosion; staff recommended and council approved the $306,882.80 low responsive bid with a 15% contingency. The project requires multiple permits including flood‑protection, Fish and Wildlife, Water Board and Army Corps approvals.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Assistant Engineer Gomez told the council the water‑main replacement will remove and replace about 227 linear feet of a water transmission main exposed by Fresno River erosion between Well Site 18 on Gateway Drive and Riverside Drive.
Gomez described a lengthy permitting process that included an encroachment permit from the Valley Flood Protection Board, a streambed alteration agreement with California Fish and Wildlife (including pre‑ and post‑activity biological surveys and a spill plan), a Section 401 certification requirement from the California Water Resources Control Board, and a US Army Corps permit. He said the city obtained the necessary permits and that the project is funded entirely by the city's water utility fund.
Bids opened July 2, 2026; four bids were received and reviewed for licensing and bid security. Gomez said the lowest responsive bid came from BNL Contractors at $306,882.80 and staff recommended awarding the contract with a 15% contingency for unforeseen conditions. He noted the engineering estimate was $294,450 and the highest bid was about $497,700.
After brief council remarks and no public comment, council moved to approve the contract award and the motion passed unanimously.