Star Valley Ranch to press ahead with road repairs after Silverstar delay; Vista Drive work slated for July 28
Summary
Town staff reported the Silverstar road project is behind schedule at about 50% completion, prompting the Town to haul road base and begin surface removal and base laying on Vista Drive beginning July 28; bids for Green Canyon tank lining opened the same day.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Administrator Aitken told the council that graders have been actively working on the north end of Town and that the Silverstar project is roughly 50% complete but behind schedule. As a result, the Town is proceeding with in-house road improvements: crews will remove existing surface material, lay new road base and prepare Vista Drive for paving with material deliveries already scheduled; work is expected to begin July 28.
The council also learned that the bid opening for the Green Canyon water storage tank lining project was scheduled for July 8 at 2:00 p.m.; the Town Engineer will review submissions and provide a recommendation. Preparations for paving bridge crossings over Cedar Creek at Hardman and Middle Branch are also underway.
Council members discussed balancing contractor schedules and in-house crews to limit delays. No formal action was taken during the work session; staff will return with bid assessments and scheduling details for forthcoming meetings.