Summary

Marion County commissioners authorized up to $24,279 to stop water intrusion damaging the courthouse interior and north stairwell, approving two bids from the same contractor and noting the work is urgent to prevent further interior damage.

A Marion County commissioner on July 13 moved and the commission approved up to $24,279 to pay a single contractor to address water intrusion at the courthouse, following staff reports that leaks have reached interior courtroom and clerk's-office walls and two stairwells.

The county clerk presented two bids: $13,009.98 to repair a warehouse wall leak and $10,002.81 for exterior north-staircase waterproofing. Facilities staff said the water infiltration is severe enough to be coming through two floors and must be stopped before interior wall repairs can proceed.

County staff said the contractor guaranteed repairs for at least a year and would return to fix problems covered by the warranty. A commissioner moved to authorize the work “not to exceed $24,279” to Hutton with a note that the contractor might reduce costs if both mobilizations are combined; the motion carried by voice vote, recorded as 4–0.

The funding will come from the county’s repair allotments in the packet; commissioners stressed the urgency because ongoing moisture is worsening interior damage and will increase future repair costs if left unaddressed. The contract award authorizes exterior waterproofing work and immediate mobilization so interior wall remediation can follow.

The commission also directed staff to confirm warranty terms and seek any available mobilization discount. No legal or procurement details beyond the vendor name and proposal amounts were provided at the meeting. The commission moved on to other agenda items after the vote.