Bremer County to allocate CHBP funds for two bridge replacements; accepts highest bid pending final review
Summary
County engineer told the board two bridge projects will be funded 80/20 through CHBP and local match; the board authorized the chair to sign agreements with the Iowa DOT and approved project-plan signatures. The board also accepted a high bid recorded as $50/ton pending Tim Meeker's final review; the public record contains inconsistent bidder-name spellings.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Bremer County Board of Supervisors authorized funding agreements with the Iowa Department of Transportation to apply CHBP (County Highway Bridge Program) awards to two bridge replacements and approved related project-plan signatures to let the DOT put the projects to bid.
County engineer Landon Moore told supervisors the projects will be funded 80% by CHBP and 20% by local match. He described the first structure (Bridge 106) as a proposed 213-foot concrete-beam bridge and said the second project will replace an existing span with a large box structure. Estimated costs on the record were about $1.8 million for the first project and roughly $1.0 million for the second; Landon said both projects are expected to go to DOT bid in November with construction next spring-summer.
The board authorized the chair to sign the funding agreements with the Iowa Department of Transportation by voice vote (ayes; chair voted aye) and approved the project-plan signatures that will allow the DOT to advertise and manage the bids.
On a related procurement matter, the board opened four bids by phone with Tim Meeker. The highest bid was recorded in the minutes as from Jason Hunnamiller at $50 per ton; the board moved to accept the high bid "pending Tim's final review and approval." The record contains inconsistent spellings of the high bidder's name in different segments; the board noted it would confirm the bidder's contact and documentation before finalizing the award.
Board action was by voice vote; supervisors asked staff to provide final bidder documentation and to coordinate with Tim Meeker for final approval.