Council accepts 6th & Maple street repair work and approves final payment to contractor

The Mayor and City Council of the City of Chadron, Nebraska · June 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Change Order No. 1 reduced the Fuller Construction contract by $2,192.38 to reflect as-built quantities; the council approved the adjusted contract and final payment of $3,622.48 to Fuller Construction for the completed 6th and Maple Street repair project.

The City Council on June 15 approved Change Order No. 1 for the 6th and Maple Street repair project, which reduced Fuller Construction Company's contract by $2,192.38 to reflect as-built quantities, and approved Payment Application No. 3 (final) directing a payment of $3,622.48 to Fuller Construction.

Janet Johnson, Planning/Building/Zoning Official, said the change order adjusts project quantities downward and noted the completed work included sod installation and construction of a retaining wall; she reported the 6th and Maple Street Repair Project is now complete.

The resolution accepting the change order sets the current contract amount at $47,654.62 (original contract $49,847.00 less the change order). The council approved the final payment after finding the materials and work had been furnished and received by the city.

The council's roll call was unanimous. The action closes the project in the city's records; the council did not record outstanding claims or further work on this contract in the meeting minutes.