Clifton council authorizes mayor to finalize Streetscape funding resolution with SPC ahead of VDOT deadline

Clifton Town Council ยท July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council authorized Mayor Hollaway to work with the Special Projects Committee to finalize a required resolution confirming the Town's cost-share for a VDOT Transportation Alternatives funding application; the resolution must be submitted to VDOT by Oct. 1 and the full funding application by Nov. 1.

The Clifton Town Council on Sept. 3 authorized Mayor Bill Hollaway to work with the Special Projects Committee (SPC) to approve a finalized resolution confirming the Town's commitment to match funding for a Transportation Alternatives funding application to the Virginia Department of Transportation (VDOT).

Town Clerk Amanda Christman summarized a report from Susan Yantis outlining current project steps for Streetscape Phase II: the Town has initiated the right-of-way (ROW) authorization phase with VDOT, which includes beginning discussions for two easements with adjacent property owners (identified in the report as Sheldon Hofferman and the Lyon family). Christman told the council that the full VDOT funding application must be submitted by Nov. 1 and that a supporting resolution confirming the Town's match is required by Oct. 1. The Special Projects Committee is finalizing how much additional funding to request and how much the Town can feasibly commit as match.

Mayor Hollaway moved to authorize him to work with the SPC to approve the finalized resolution; the motion was seconded by Vice Mayor Effros and approved by roll call (Hinderstein: Aye; McDonald: Aye; Milne: Aye; Hollaway: Aye; Effros: Aye; Poe: Aye).

Why it matters: Streetscape Phase II is the Town's multi-year capital project; the council's action preserves the Town's ability to apply for state-managed transportation funding and signals continued local commitment to move the project through ROW and easement negotiation.

What's next: the SPC will finalize requested additional funding and a match amount; the Mayor is authorized to sign the cover page for the recommended-for-approval ROW acquisition as needed during the VDOT process.