Superintendent Dr. Lohr told the Kiski Area SD board the intermediate school has received partial occupancy while several inspections and fixes remain; he also said a pool building is being erected on campus with help from a Doo2Cable donation.

Superintendent Dr. Lohr said the district has received "a partial occupancy for the intermediate school" while a handful of safety and systems items remain before full occupancy. He listed adjustments needed to the fire-system detectors, reinforced air-return components, some hot-water corrections and a required elevator inspection. "The kitchen passed the building inspection," he added, but said the Department of Health must complete its inspection before that area can be used.

Dr. Lohr also said work has begun on a pool building behind the campus, attributing progress to "some generous donation" and a contribution of electric and internet services from Doo2Cable. "If you've driven to the back of campus you see that the pool building is being erected there," he said, and thanked donors by name.

On operations, Dr. Lohr said most administrators are taking summer leave while staff plan professional development and preparation for the new year. He told trustees a hard copy of the collective bargaining agreement requested by the board has been provided for review. Separately, staff reported difficulties with a scheduling software vendor after a corporate buyout; staff said fixes made the online schedules "95% accurate" and pledged the schedules would be 100% correct by the end of the week or, if not, to post an accurate temporary Google Doc while the vendor issues are resolved.

The report did not include dates for final occupancy or a dollar estimate for the pool project; those details were not specified in the meeting discussion. Next procedural steps noted by the superintendent included completing the outstanding inspections and returning to the board with any remaining compliance items for approval.