Gary parks staff report progress on Leech access pad, staff increases and boat‑launch problems

City of Gary Department of Public Parks park board · July 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Maintenance staff told the Gary parks board they completed a handicap access pad at Leech but face compaction and drainage issues; they are testing sand and crushed rock fills. Staff reported hiring an additional maintenance worker (bringing on‑site staff to four), pavilion rentals are fully booked on weekends, and the boat launch remains nonfunctional because of persistent north winds and manpower constraints.

Park maintenance staff reported to the Gary parks board on July 17 that crews completed a handicap access pad at Leech but are managing compaction and surface issues in pea gravel. Staff said they have tested adding sand to act as a binder and may use crushed rock fines to stabilize the surface before compacting again.

The deputy director of public works has hired an additional worker to assist maintenance crews, increasing on‑site staff to four, staff stated. Park shelter and pavilion rentals are heavily booked on weekends, with multiple events including a wedding and a baptism noted for the coming weekend.

Staff also said the Marquette Park boat launch remains nonfunctional due to recurring north winds and persistent standing water that prevent safe operation. Maintenance staff cited manpower and weather as the main constraints on restoring boat‑launch availability.

The board requested continued updates and thanked maintenance staff for ongoing work.