Commission favors spillway/levee crossing for Greater Pond trail rather than a ford or costly bridge

Water Resource Management Commission · July 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After design review, staff recommended a spillway/levee-style paved crossing for the Greater Pond trail because a forward/ford crossing could be inundated for extended periods; commissioners flagged ADA and permitting questions and asked for final cost comparisons.

Staff gave a design update on alternatives for a trail crossing at the downstream outlet of Greater Pond and recommended a spillway/levee-style paved crossing over a forward (ford-type) crossing or an expensive bridge.

"Assuming it's already filled up to the top, if we get a one‑year storm event and we have a forward crossing, the path would be inundated for 60 or more hours straight," the staff member said, explaining why a spillway/levee crossing would keep the trail more usable in common storm scenarios.

Staff said the bridge alternative, while it would avoid temporary inundation, was not included in the earlier $300,000 cost estimate and could substantially increase construction and future maintenance costs. Commissioners raised ADA accessibility concerns and asked staff to return with a final cost recommendation and confirmation of DNR permitting constraints before moving to final design.

Staff said 30% plans from MSA are under review and that the project will return for further Commission review as design advances. No final commitment was made at this meeting; staff will bring refined cost estimates and a recommended preferred alternative in a future packet.