NPPD tells Logan County construction under way south of Stapleton; work paused north of Stapleton and east of Thedford

County Commissioners and Board of Equalization of Logan County, Nebraska · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Nebraska Public Power District informed the board construction on the R-Project 345 kV transmission line has begun south of Stapleton; soil-disturbing activities north of Stapleton and east of Thedford are paused while right-of-way negotiations and access surveys continue.

Paul Brune of Nebraska Public Power District and construction managers from WSP and Forbes Bros updated the Logan County Board on the R-Project 345 kV transmission line on July 15.

Brune said construction has begun south of Stapleton, and that soil-disturbing activities north of Stapleton and east of Thedford have been paused. NPPD will continue right-of-way negotiations, access surveys, mowing and staking for access routes and structures in the paused areas, the meeting record states.

The update noted continuing outreach and coordination tasks (negotiations and surveys); the transcript does not record specific timelines, estimated completion dates, or parcels for construction in the paused area. No formal county action on NPPD’s update was recorded at the meeting.