Property owners from the East Bluff area told the Decatur Mayor and Board of Aldermen they cannot obtain building permits after plats filed by a developer; city staff and residents said the solution likely requires TDOT driveway permits, a replat or planning-commission variances and could expose large infrastructure costs.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
Darryl Meredith and other residents from the East Bluff subdivision told the Decatur Mayor and Board of Aldermen on July 14 that they have been unable to obtain building permits after a developer recorded plats they say conflict with planning-commission guidance. "My name is Darryl Meredith. I own property on East Bluff, and I'm not sure exactly what's going on except that we can't get permits," Meredith said during the public-comment period.
Residents described a sequence in which a developer's surveyor presented a plan to the planning commission, was told changes were needed, then recorded a plat in a different form. Several speakers said the town and the state interpret Tennessee subdivision law to treat lots under 5 acres or those requiring new infrastructure as subdivisions, which triggers permitting requirements. "It's 5 acres or if these other things happen, which would possibly pull this into a subdivision," one participant explained during the meeting.
City staff and others told the group that three practical paths could allow property owners to move forward: (1) obtain TDOT driveway permits that would allow multiple accesses and enable the planning commission to consider variances; (2) replat the lots so individual parcels have allowable access or shared access consistent with TDOT guidance; or (3) accept a county process if de-annexation is pursued, though staff cautioned that county rules may present the same subdivision constraints. City staff repeatedly emphasized that TDOT's decision on driveway permits is pivotal.
Speakers also raised cost and service concerns. One city representative said that extending city water and fire service to the East Bluff area — including hydrants and associated infrastructure — could cost on the order of $2,000,000, and that such work would normally be the developer's responsibility. "To provide water to that section and put in the... fire hydrant and everything that would be required under subdivision, you're looking at almost $2,000,000," a speaker said.
Residents asked about short-term relief such as private roads or smaller shared access, and staff said the planning commission can consider variances that reduce certain standards if TDOT authorizes access points. Several residents urged the board to avoid protracted litigation and to seek a pragmatic replanning route instead: "We need to find a way to bring you into the community instead of... kicking the can," a speaker said.
The meeting did not produce a final decision on de-annexation, developer liability or immediate building permits. City staff said they would follow up with TDOT to determine how many driveway permits are available for the corridor and that replatting or a planning-commission variance may follow TDOT guidance. Residents were invited to the planning commission and encouraged to work with a surveyor and the planning commission if replatting is chosen.
Next steps: staff will report back to the mayor and board after contact with TDOT and after any follow-up planning-commission consideration; residents were told the planning commission could entertain variances depending on TDOT access determinations.