Commission tables Norborn Glebe performance bond release, approves land-disturbance release
Summary
The commission tabled the $819,036 performance bond release for Norborn Glebe Phase 14B until remaining streetlights are installed by the utility, and approved release of the $123,437 land-disturbance bond after staff review.
Get email alerts on the Development And Infrastructure topic
No spam. Unsubscribe anytime.
At the March 24 meeting the Planning Commission reviewed a bond-release request for Norborn Glebe Phase 14B. Staff reported the performance bond was $819,036 and the land-disturbance bond was $123,437; the submitted plan called for 30 streetlights but inspectors verified only 22 installed lights. Staff and the bond committee recommended tabling the performance-bond decision until the outstanding eight streetlights are installed by FirstEnergy.
The applicant’s representative (Michael Hummel, Arcadia Land Inc) acknowledged the discrepancy and said the team is coordinating with FirstEnergy to complete the installations. After opening and closing the public hearing the commission voted to table the performance-bond decision until the lights are installed and to approve release of the land-disturbance bond. Staff noted tabling avoids re-advertisement and extra procedural steps that denial could require.