Summary

Bids were opened for the Fiscal Year ’23 Cattle Congress sanitary sewer lift station reconstruction, contract No. 1075. Clerk read three bids — Wendler ($2,966,361.40), Peterson Contractors Inc. ($4,230,069.05) and Boomerang Corporation ($5,097,512.50) — and noted each provided 5% bid security.

The clerk opened a public bid reading for fiscal year ’23 Cattle Congress sanitary sewer lift station reconstruction, identified in the notice as Contract No. 1075, and read three bids for the project.

The clerk read Wendler of Anna Amana, Iowa, as the lowest bidder at $2,966,361.40 and stated Wendler had provided the required 5% bid security. Peterson Contractors Incorporated of Rhinebeck, Iowa, submitted a bid of $4,230,069.05 and likewise provided 5% bid security. Boomerang Corporation of Anamosa, Iowa, was read as a bidder; after an initial uncertainty about formatting the figure, the clerk corrected the entry to $5,097,512.50 and recorded that Boomerang had provided a 5% bid security.

"$5,097,512.50," the clerk said when stating Boomerang’s corrected total. The transcript shows the clerk reading each bidder’s name, location, and total and noting the 5% bid securities for each submission.

The reading of bids was recorded in the session; no award, motion, or vote on the contract appears in the transcript. The clerk closed the reading with, "Thank you for your bids." Next steps — including any evaluation, recommendation or award timeline — were not stated in the recorded sequence.