Board tables decision on 4" water main for JMHP, schedules stakeholder meeting
Summary
Employee Mattley reviewed engineer plans for a 4" water main into the JMHP trailer park; trustees agreed Mattley, Trustee Scott, JMHP owner Brandon Maendele and the village engineer will meet next week to review plans, and the board tabled the item pending that meeting.
Get email alerts on the Water Service topic
No spam. Unsubscribe anytime.
Employee Mattley presented plans from the village engineer for a new 4" water main to serve the JMHP trailer park. Board members discussed several options but did not take final action.
Trustee Scott, Mattley, JMHP owner Brandon Maendele and the village engineer were directed to meet next week to review the plans in detail. The minutes state the item was tabled pending that meeting; no vote, cost estimate or construction schedule is recorded in the minutes.
Because the board did not adopt a final plan or vote a funding source at the July 9 meeting, further technical review and a future board action will be required before construction or procurement can proceed.