Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Wastewater Repairs topic
No spam. Unsubscribe anytime.
Winfield flags higher-than-expected wastewater pump costs; counsel to write to Thrasher
Summary
Council members were told initial $70,000 estimate from Thrasher to repair a cake pump rose after further estimates; legal counsel will write to Thrasher and new equipment has a roughly 16-week lead time once ordered.
Get email alerts on the Wastewater Repairs topic
No spam. Unsubscribe anytime.
Winfield City Council discussed an equipment failure at the city wastewater treatment plant and the prospect of higher repair or replacement costs than an initial estimate indicated.
Council heard that Thrasher initially offered $70,000 to correct issues with a cake pump at the plant but that more thorough estimates put the cost significantly higher. Legal counsel Tim Lafon said he would draft a letter to Thrasher to address the discrepancy and next steps.
Officials were also told that if the city proceeds to order new equipment, lead time is roughly 16 weeks. The plant was described as "running good" otherwise, and plant staff were recognized for recent work clearing snow from streets.
Council did not vote on a specific procurement at the Jan. 14 meeting; the discussion centered on cost estimates, a planned formal notice to the contractor, and the scheduling implications of a multi-month equipment lead time.
