City manager outlines timelines for Noma Drive, Comey Drive and other Diamondhead projects

Diamondhead City Council · May 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Manager John updated the council on multiple public works projects: Noma Drive punch list remains, dredging and channel markers near completion, Comey Drive change order reduces cost by ~ $10,000 but extends schedule to June 10, and multiple other projects (MDOT ramp, bridge deck pours, dog park, paving) are progressing.

City Manager John briefed the Diamondhead City Council on the status and near-term timelines for a slate of infrastructure projects during the May 20 meeting.

"The Noma Drive... ribbon cutting was a wonderful event," John said, noting contractors still have a punch list of items to finish. He reported the Noma dredging project is complete and that a hydrographic survey will be finalized in the next few days before channel markers are installed to aid boaters.

John said the Comey Drive / Callepona Pond project is a 120-day contract with a current end date of June 10. He described a change order on the agenda to slightly reduce the overall contract price ("a little over $10,000") while extending time to account for weather-related delays; the change includes an adjusted anchor system for conduit to prevent buoyancy problems.

Other updates included the MDOT ramp work with an anticipated paving window by the end of the month, bridge deck pours underway in sections, completion of survey work for a proposed dog park, a 2025 paving preconstruction meeting scheduled for the coming Friday, and a Coomb Branch project with a notice to proceed set for June 16 and an expected completion in December.

Council questions were limited. Councilman Clark asked whether the city had formal discussions with the POA about a specific project; John said only informal conversations have occurred so far and no formal meeting has been scheduled.

Why this matters

The project updates define near-term construction impacts, timelines for public works, and administrative steps the city will take to close out current contracts and begin new ones. The change order on Comey Drive and the schedule for Coomb Branch and canal projects are likely to affect neighborhood access and contractor timelines.

What’s next

Staff will complete Noma Drive punch-list items, install channel markers for the dredging project, finalize change-order paperwork for Comey Drive, and proceed with scheduled preconstruction and notice-to-proceed milestones.