Votes at a glance: Ripon council approves park, library, utility and street pay applications, wastewater valve work and an appointment
Summary
The Ripon Common Council approved multiple pay applications and a wastewater valve replacement contract, accepted reports, and confirmed an appointment to the Historic Preservation Commission during the meeting.
Get email alerts on the Municipal Finance topic
No spam. Unsubscribe anytime.
The Ripon Common Council approved a series of routine and project-specific items by voice vote during its meeting, including multiple pay applications, a wastewater plant valve replacement contract, and an appointment to the Historic Preservation Commission.
Key votes and outcomes
- Pay application No. 6 (Selfridge Park) — $125,606.68: Approved. Staff reported roughly $143,308.39 remaining on the project budget and said piers and installation are expected later in the summer.
- Pay application No. 10 (Ripon Public Library renovation) — $216,210.50: Approved. Staff said the original grant funding has been exhausted and remaining funds will be covered by the library budget; the project is in phase 3.
- Pay application No. 1 (SCADA system upgrade) — $36,290.05: Approved. Staff described the SCADA upgrade as an early phase of an approximately $1,000,000 project and reported a recent radio study had gone well.
- Pay application No. 1 (Houston Street reconstruction) — $27,154.37: Approved. Staff said the project is about three weeks behind schedule after subcontractor delays and that rock was encountered during excavation, which might prompt a change order.
- Wastewater plant influent valve replacement — Crane Engineering quote $25,689.66: Approved. Staff recommended replacing four aging discharge valves and funding the work from the equipment replacement fund; council approved the unbudgeted equipment expenditure.
- Historic Preservation Commission appointment — Kate Salas (term through Oct. 2028): Approved.
Other procedural matters such as accepting standing committee and staff reports, the consent calendar and approval of the meeting agenda were also passed by voice vote.
What’s next: Contracts and final payments will proceed according to project schedules, and staff will return to the council as needed for any formal contract awards or change orders.