Electric utilities close AMI contract with tariff change order, award tree-trimming bid

High Point City Council Finance Committee · July 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Electric utilities director Tyler Barrier asked the committee to approve a $102,198.12 final change order to cover tariffs on the AMI contract with Tantalus and to award a per-circuit tree-trimming contract (approx. $1.75 million); staff outlined resident notification plans for trimming work.

Tyler Barrier, the city’s electric utilities director, told the committee the Advanced Metering Infrastructure contract with vendor Tantalus is being closed and the department is requesting a final change order for $102,198.12 to cover tariffs assessed because the vendor is Canadian. Barrier said Tantalus initially covered part of the tariff but later stopped; the city absorbed roughly a 10% tariff. He added that Tantalus is applying for tariff refunds and, if refunds are received, there is a possibility the city could be reimbursed, but the city is not relying on that outcome as it closes the contract.

Barrier also presented a new annual approach to tree trimming for the electric system. The department solicited per-circuit bids for trimming roughly 450 miles of overhead transmission/distribution; six bidders qualified and the recommendation was to award to Aspen with a contract figure discussed at about $1,750,000. Barrier described public outreach measures including printed door hangers, a contractor phone number on the notice, and reverse call/text alerts to notify residents before crews enter neighborhoods.

The committee approved the AMI change order and the tree-trimming contract by motion.