Commissioners review $2.09 million GO North pre‑application for Riverside Rest Home renovations
Summary
County staff told the Board that a GO North pre-application submitted June 25 requests about $2,090,000 to replace the roof, boiler and windows at Riverside Rest Home; the county expects a $2,000,000 cap and is lining up grant-writing support before a Sept. 1 application deadline.
Get email alerts on the Nursing Home Renovation topic
No spam. Unsubscribe anytime.
County staff told the Strafford County Board of County Commissioners on July 16 that the county submitted a GO North pre‑application on June 25 seeking about $2,090,000 to fund three projects at the Riverside Rest Home: a new roof, a replacement boiler and window upgrades.
Diane, a county staff member, said the total for the three projects "came out to, like, $2,090,000," and added, "I think it's capped at 2,000,000, but we asked for it anyhow." She said the county also requested technical assistance money for grant writing and that Stratford Regional Planning has applied to be considered as the grant writer for the application.
Why it matters: the work is aimed at correcting deferred capital needs at a county‑run nursing facility; GO North appears to favor "shovel‑ready" projects and the first round is moving on a tight timeline, staff said.
Commissioners and staff discussed who would prepare a full application if the project advances. Diane said the county has flagged Stratford Regional Planning as a likely external grant writer but that commissioners will make the selection "as soon as we understand what we're selecting." Commissioners emphasized the need to be prepared for the short application window and noted projects should show concrete start dates and readiness to proceed.
The board was advised the GO North application deadline is Sept. 1. Diane and staff said they would forward any additional material requested by the administering agency and return to the board with updates.
Next steps: staff will wait to hear from the administering agency and will return to the board with more information and a recommendation for grant-writing support if the county is invited to submit a full application.