Fire and road departments report on calls, paving, culverts and project milestones
Summary
Fire Chief reported 509 calls for service so far in 2025 and a tanker due in 2026; the road superintendent described completed rehab work on Cambridge Ave, paving in Hillers subdivision, culvert replacements, and rising sign theft. Administrator Guzman updated on design‑build kickoff and 2026 budget work.
Get email alerts on the Operations Reports topic
No spam. Unsubscribe anytime.
Chief Chad Lady told trustees the fire department has run 509 calls so far in 2025, has met with HTK regarding the bond vote, met with Weis Fire about a new tanker expected for delivery in 2026, and is pursuing a grant to buy new hire gear.
Road Superintendent John Tipton reported two entrance permits were issued in May, the Cambridge Avenue rehab was completed (curb, road base repairs, two‑inch overlay, backfilling, grading and seeding), paving has begun in the Hillers subdivision, a crossroad culvert replacement was completed on NW 39th Street, and multiple driveway culverts were replaced. He also noted that right‑of‑way mowing is ongoing (third pass) and that sign theft has increased.
Administrator Audree Guzman said concrete core samples were scheduled at the Road Maintenance Shop on June 10, a design‑build kickoff for the new fire station occurred June 6, an open house is planned for October, and work on the 2026 budget will be presented at the August meeting. Guzman also noted an RNR notice to the county is due in July and that she has been spending one day a month with each fire shift since April.
Why it matters: the reports outline near‑term capital and maintenance activity that affect road safety, emergency response capability and timing for the township’s bond and budget decisions.