Wakefield council approves $19,524 change order and $31,563 payment for sidewalk project

Wakefield City Council · December 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 1 adding $19,524 to a CDBG-funded Sidewalk Project for width adjustments, unforeseen removals and a second retaining wall, and approved the contractor's third payment request of $31,563; the State extended the project deadline to June 30, 2026.

Administrator Mike Mogus presented Change Order No. 1 from Jeremy Kumm of Dirt Road Construction that increases the cost of the Sidewalk Project by $19,524. The change order covers sidewalk width adjustments, unforeseen removal of existing sidewalk beneath sidewalk, added equipment rental and construction of a second retaining wall at South Main Street and Kerri Avenue. The state granted a completion extension through June 30, 2026.

Council Member John Geiser moved to approve Change Order No. 1 and Council Member Dolen seconded; the motion carried with Dolen, Geiser and Hansen voting aye (Brenn absent). The council later approved Dirt Road Construction’s third payment request, dated Nov. 18, 2025, in the amount of $31,563.

The project is funded with remaining Community Development Block Grant (CDBG) funds. Mogus presented the change order and payment request as part of routine project administration; no additional funding source changes were made during the meeting.

The city will proceed under the new project budget and the state-approved timeline; staff will continue to report project progress to the council.