Superintendent: transformer move will cause two‑day outage; Certificate of Need filed and preconstruction meeting set
Summary
Superintendent Paul Peppmeier told the board the district will be without power for about two days when a transformer is moved in mid‑to‑late June; the Certificate of Need has been submitted to the state and a preconstruction meeting is scheduled for May 26 at 2:00 p.m.
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
WEST BEND — Superintendent Paul Peppmeier updated the West Bend‑Mallard Comm School District board on several facilities items at the May 19 meeting, including a planned transformer move, a city request for a stem wall and a pending Certificate of Need filing.
Peppmeier said the City has asked the district to provide a stem wall for a new pickleball court; the district’s estimate for that work is $6,700. He also said the district is scheduled to move a transformer in mid‑to‑late June; the district expects the operation will leave the site without power for about two days while crews complete the work.
Peppmeier reported the district submitted a Certificate of Need to the state and anticipated a response around June 9. He told the board a preconstruction meeting is scheduled for May 26 at 2:00 p.m. in the board room to advance upcoming projects.
The board approved related contracts and construction‑adjacent decisions during the same meeting; follow‑up items include finalizing contractor scopes and budgets at or after the preconstruction meeting.