Plan commission unanimously extends Mandel Group's Delafield Street permit deadline to Nov. 19, 2028
Summary
After hearing public comments and staff updates about a pending lawsuit and an unresolved historic-preservation easement, the Waukesha Plan Commission approved a two-year extension for Mandel Group's approved 219-unit development at 130 Delafield Street.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
The Waukesha Plan Commission voted unanimously to extend the plan-approval deadline for Mandel Group's approved 219-unit development at 130 Delafield Street to Nov. 19, 2028. Staff told the commission the extension responds to litigation and an unresolved conservation-easement process that prevent the city from transferring title to the developer.
At the start of the meeting, public commenter Lisa Saub urged the commission to reject the extension. "I am opposed to this extension for the reasons that I have mentioned at previous plan commission meetings, and I ask that you please vote against it," she said. A neighborhood resident who identified herself only as Melissa told commissioners that "extending approvals to late 2028 is not insignificant" and asked staff to confirm the project's fiscal projections given rising construction costs and interest rates.
Doug, the city planner presenting the item, said the developer requested the time because of circumstances outside its control: a neighboring property owner's lawsuit that has been appealed to the court of appeals and a pending conservation easement with the state historical society. "There's a couple of things out there that are outside the scope of the control of the developer," he said, adding that the city has amended the purchase agreement to extend the closing date until both the lawsuit and the easement are resolved.
Sarah Hillenbrand of Mandel Group told the commission the developer remains committed to the project and is seeking the extension only to complete the property transfer after the outstanding matters are settled. Alderman Eric Payne, representing the district that includes the site, urged denial and noted past requests for extensions that had been refused; he said the commission should be cautious about repeatedly extending approvals.
Commissioners discussed conditions: several emphasized that any material changes to the approved plans would require the developer to return for further review. Commissioner Keller specifically urged that the extension not be used as permission to alter the approved design without reapproval.
The commission's motion, made citing the unresolved issues outside the developer's control, extended the permit deadline to Nov. 19, 2028; the motion passed unanimously. The action preserves the existing approved plan for the length of the extension and keeps any plan changes subject to subsequent review.
Next steps: if the litigation or easement issues extend beyond the new deadline, the developer would need to seek another extension or submit a new application; otherwise staff will await transfer of title and permit filings.