Ely Council awards Morley sewer contract, creates landfill capital fee and orders annual utility reviews
Summary
Council awarded the CDBG-funded Morley Avenue sewer upgrade bid to Reck Brothers LLC for $399,999.77, established a $2/month landfill capital improvement fee (estimated $144,000/year), approved a state NDOT reimbursement agreement and a policy for annual water/sewer/landfill rate reviews, and authorized RFQs for future engineering and surveying contracts.
Get email alerts on the Utilities Infrastructure topic
No spam. Unsubscribe anytime.
At its Aug. 14 meeting the Ely City Council approved a series of utility and infrastructure actions aimed at completing ongoing projects and creating dedicated capital funding.
The council awarded the Morley Avenue Sewer Main Upgrade (CDBG Project 24/PF/01, PWP# WP-2025-206) to Reck Brothers LLC for $399,999.77 after the city engineer reviewed bid materials and found Reck Brothers the lowest responsive bidder. City Engineer B.J. Almberg recommended the award so construction can proceed this fall.
To build a fund for major landfill equipment replacement, particularly a compactor that has required roughly $500,000 in repairs to date and whose replacement cost is estimated at about $1 million, the council adopted Resolution 2025-07 to establish a $2.00-per-month Landfill Capital Improvement Fee effective Sept. 1, 2025. City Treasurer Janette Trask estimated the fee will generate approximately $144,000 annually.
The council also approved an Agreement for Reimbursement of Construction Engineering Costs with the Nevada Department of Transportation that consolidates prior cost-accounting and will allow the City to receive outstanding reimbursements. Council adopted Resolution 2025-08 requiring the governing board to review water, sewer and landfill rates annually during the second meeting in January, a condition cited by state financing staff reviewing Morley grant applications.
Other actions included: removal of specified past-due utility penalties for three properties per Municipal Utilities Board recommendations; creation of a vehicle-impound lot on part of APN 001-49-113 for code-enforcement towed vehicles; extension of Basin Engineering’s consulting agreement through June 30, 2027, with staff directed to issue RFQs for civil engineering and surveying services to commence July 1, 2027; and authorization of a plan to place wireline-easement income and 45G tax-credit proceeds into restricted capital funds for City Hall renovation.
Councilmotions on these items were unanimous where recorded. A proposed Revolving Loan Fund loan for a new garage business was tabled after legal/conflict concerns, and staff was directed to review signage and traffic safety on Murry and Campton Streets and report back.