Bainville approves contract amendment for town water project

Bainville Town Council · September 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved and the mayor signed a Notice of Award and Contract Amendment #2 with Interstate Engineering for the town water project and was briefed that August water loss was 414,102 gallons (23%), above the town goal of 10%.

The Bainville Town Council reviewed an update on the town’s water project and approved a Notice of Award and Contract Amendment #2 from Interstate Engineering; the documents were approved and signed by Mayor Toby Romo during the Sept. 9 meeting.

Council members received a separate water-loss report showing the town lost 414,102 gallons in August 2024, equal to 23% loss; the minutes note the town’s goal is 10% or less. The water project documents and contract amendment are recorded in the meeting’s Department and Committee Reports and were executed by the mayor.

The minutes do not record dissent or a roll-call vote for the contract amendment; they state the contract documents were approved and signed by Mayor Romo. The town indicated follow-up work on the FY 2024–25 Annual Budget and operational items will be handled by Clerk Billie Jo Cochran and staff in upcoming meetings.