District proposes moving 6th-grade academy into high school wing during middle-school construction

Pojoaque Valley Public Schools Board of Education · March 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

To avoid portable classrooms during middle-school construction, the district proposed temporarily locating the 6th-grade academy in an East wing of Pojoaque Valley High School with dedicated classrooms, restrooms, staggered lunches and an accordion gate for separation; board members asked detailed safety and supervision questions.

Pojoaque Valley Public Schools staff proposed temporarily relocating the 6th-grade academy to the East wing of Pojoaque Valley High School during the upcoming middle-school construction to avoid portables and portable restrooms.

Associate Superintendent Vigil and Superintendent Segura described a student-centered plan that designates six classrooms for 6th-grade instruction, dedicated restrooms, a shared SGA office for principal and counselor, staggered lunch periods, a separate drop-off/pick-up area, and a visible physical barrier (an accordion gate) to separate 6th graders from the high-school population. The PBHS math department would move into currently vacant classrooms to free space.

Officials said elective classes would be taught by high-school or middle-school teachers in scheduled blocks to minimize unsupervised movement and that the SGA principal and counselor would remain accessible within the wing to preserve continuity of leadership. A letter to incoming 6th-grade families and staff communication were planned to explain logistics.

Board members asked specific questions about classroom locations near ISS, camera-room access, special-education spaces, transportation location and egress safety. One board member raised a concern about an accordion gate in an emergency and stressed that crash-out egress hardware and clear evacuation plans must be ensured; district staff said existing accordion gates are in use elsewhere on campus and that they would plan for security and emergency egress procedures.

Staff framed the relocation as a temporary, student-centered alternative intended to preserve instructional quality and the 6th-grade academy identity during construction; no formal board action was taken at this meeting beyond discussion and questions.