Goshen aviation board ratifies runway substantial-completion, approves reimbursements and grant amendment requests

Goshen Board of Aviation Commissioners · July 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a July meeting, the Goshen Board of Aviation Commissioners ratified the runway project's certificate of substantial completion, authorized closeout signings, approved contract amendments and multiple reimbursement requests, and agreed to seek additional grant funds to cover change-order overages.

The Goshen Board of Aviation Commissioners voted in July to ratify the runway project's certificate of substantial completion and approved a series of related contract amendments, pay requests and grant actions intended to close out the project.

Daniel, the airport engineer, told the board the runway work is essentially complete and that issuing the certificate of substantial completion starts the one-year warranty period. "We did go ahead and issue the certificate of substantial completion, which basically says this is pretty much done, and we're gonna go ahead and start the warranty period," he said. The board moved to ratify the certificate and approved the motion by voice vote.

The board approved a $15,560 amendment to address additional quality-assurance testing on asphalt and coordination related to failing tests; the local share cited in the agenda was about $389. Members also approved a request for reimbursement (RFR) of $33,185.53 to Wilbur services (as recorded in the meeting materials) and two milestone pay requests to Milestone for $153,760.43 and $514,310.10, which the engineer said will leave the local share around $16,000.

On grant funding, the engineer told the board the FAA allows grant amendments to cover substantial change orders but that this project exceeded the usual threshold; he said H2 Aviation agreed to cover the share of the overage. The board approved sending a grant-amendment request letter to the funding agency and authorized the airport manager to sign closeout documents and requests for reimbursement.

Chair Greg Lanson praised the work. "You did a great job for us," he told staff and contractors, noting the board appreciated that the project finished earlier than expected. The engineer also said the project came in under budget by nearly $500,000 and described the work as an "awesome project."

What this means: the certificate of substantial completion begins the warranty clock for contractor remedies, the board authorized staff to complete grant closeout paperwork, and the board approved contractor payments and a small local contribution to finish project accounting. The airport manager and staff will return with quotes for replacing an aging runway-light regulator and for any other equipment replacements related to a subsequent power-surge incident.

Votes at a glance - Ratify runway certificate of substantial completion: approved (voice vote). - Approve contract amendment for additional asphalt testing, $15,560 (local share ~$389): approved (voice vote). - Approve RFR to Wilbur services, $33,185.53: approved (voice vote). - Approve milestone pay requests to Milestone, $153,760.43 and $514,310.10: approved (voice vote). - Approve grant-amendment request and authorize airport manager to sign closeout documents: approved (voice vote).

Next steps: staff will submit the grant-amendment letter and RFRs, provide written cost estimates for any regulator replacement and runway-light repairs at a future meeting, and continue project closeout steps.

(Reporting note: motions and voice-vote outcomes are recorded in the meeting transcript; individual roll-call tallies were not recorded.)