Mayfield board approves MHS renovation final documents and $11.7 million cost estimate

Mayfield Independent School Board · October 21, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Mayfield Independent School Board unanimously approved BG 23-113 final construction documents for the Mayfield High School renovation and accepted the KDE BG-3 Statement of Probable Cost listing $11,734,805 as the estimated project cost.

The Mayfield Independent School Board voted unanimously Oct. 21 to approve final construction documents for the Mayfield High School renovation and addition and to accept the KDE BG-3 Statement of Probable Cost, which lists the project at $11,734,805.

Board member Lorane Smith moved to approve the BG 23-113 Final Construction Documents for the MHS renovation and addition; board member Martha Wynstra seconded the motion and the vote was unanimous. Separately, board member Larry Jackson moved to approve the KDE BG-3 Statement of Probable Cost ($11,734,805); board member Joe Green seconded and the motion passed unanimously.

The filings recorded in the meeting reflect formal approval of the project documentation and the district’s estimate of probable cost. The transcript records the dollar figure but does not include discussion in the meeting about funding breakdowns, specific funding sources, or next administrative steps beyond the approvals.

The votes were taken as part of routine board business and were recorded as unanimous. The board continued with remaining agenda items and later adjourned the meeting.