PSAP board reviews IT resiliency: spare workstation, upgrades and a geo-diverse fiber route
Summary
Bayfield County IT director described needs for after-hours support, a central knowledge base, larger hard drives for ECC computers (about $1,000 each), one spare workstation, and a geo-diverse fiber route in Washburn with an annual subscription cost of roughly $1,200–$2,000 that the PSAP grant does not cover.
Get email alerts on the It Resiliency topic
No spam. Unsubscribe anytime.
Bayfield County IT Director Paul Houck briefed the Ashland–Bayfield PSAP Board June 18 on multiple IT resiliency items, including on-call support, a knowledge base, hardware upgrades and a geo-diverse fiber plan.
Houck recommended limiting on-call IT obligations to Emergency Communications Center staff rather than extending responsibility to jail or deputy services, saying after-hours response currently occurs at-will by county IT staff. He also proposed a centralized knowledge base and time-tracking tool for ECC administrative tasks to document issues and solutions and to support grant reimbursement for labor.
The board discussed hardware needs: ECC computers purchased in 2024 require larger hard drives at an estimated $1,000 per machine; two workstations need weekly maintenance. Houck proposed a single spare ECC workstation that could be kept offline and maintained until needed; Quaderer asked whether the mobile unit could serve as a spare, and was told the mobile unit is phone-only.
Houck described work with Norvado to create a geo-diverse fiber route in Washburn to reduce outage risk, but noted Bayfield County does not subscribe to an automated WISCOM failover service. He said the proposed subscription would cost approximately $1,200–$2,000 per year and is not allowable under the PSAP grant because it would be treated as a utility payment. The minutes note Ashland County still has a single fiber run and therefore a residual single-point vulnerability.
Board members agreed to have Grady and Abeles-Allison meet separately on on-call IT issues and report back at a future meeting. The PSAP later voted to enter closed session and adjourned.