Commissioners accept auditorium HVAC quote, agree not to start construction until full funding is secured

Alleghany County Board of Commissioners · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board accepted the lone bid for auditorium HVAC work from Stanley Heating & Air and discussed funding gaps for gas/heating work and seating repairs; commissioners emphasized that accepting the quote does not obligate immediate construction and said additional grant funding will be sought. The county manager also highlighted plans to modernize the county transfer station.

County operations director David Spicer presented the results of an RFP for replacing or repairing the auditorium heating/air system and said Stanley Heating & Air was the only bidder; the packet lists details (ductwork, electrical, and two 15‑ton units). Spicer said the board had reissued the RFP and contacted local contractors but this remained the sole responsive bid.

Commissioners asked whether the project had been budgeted. Spicer said $375,000 is associated with the bid work; board members noted a project budget figure of about $390,000–$400,000 when combined with partner contributions (TDA, school system and county shares) and a previously pledged $25,000 toward seating. Spicer and others said the heating system (boiler) remains functional for the short term but the county wants air conditioning in place for upcoming events; gas-line work and tank installation for heating were not yet budgeted and would likely require additional grants or partner funding.

After discussion about contract timing and the need to secure remaining funds, a motion to accept the Stanley Heating & Air quote was made and approved by the board; commissioners emphasized that accepting a quote does not authorize immediate construction and that work would wait until funding is secured. Separately, the county manager reiterated that the transfer-station redesign is a top infrastructure priority and that an RFP for a new facility is in process.

The board discussed seat repairs and possible grant support; no immediate additional county appropriation was authorized at the meeting.