Consultant warns Bloomington wastewater plant needs multi-year upgrades, recommends UV and equipment replacements

Village of Bloomington Board · November 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Delta 3 presented an evaluation finding the 1983 wastewater plant operates at about 57% of design flow but lacks capacity for newer DNR limits; recommendations include replacing obsolete controls, switching from chlorine to UV disinfection, building new sludge storage off the floodplain and pursuing grants for a 2028–29 construction window.

Jordan Fure of consultant Delta 3 presented a draft Wastewater Treatment Facility Evaluation to the Village of Bloomington Board on Nov. 3, outlining a multi-year plan to address aging equipment and newer Wisconsin DNR requirements.

Fure said the current plant—installed in 1983—operates at roughly 57% of design flow but was not configured for modern permit limits such as ammonia, E. coli (formerly fecal coliform), PFAS, chlorides and total phosphorus. Delta 3 identified several immediate technical problems: an obsolete motor control center with hard-to-find parts, a high-wear comminutor, a generator that currently powers only one blower and is nearing the end of its useful life, a chlorine disinfection system that presents dosing and chemical-handling concerns, a sludge storage tank located in the floodplain in poor condition, and energy-intensive blowers.

To address those issues, Delta 3 recommended replacing the motor control center with variable frequency drives, improving the headworks with a mechanical screen and automatic bagger, replacing chlorine disinfection with UV disinfection, constructing a new sludge storage tank outside the floodplain, replacing blowers and adding sound enclosures, and installing a dissolved-oxygen probe to regulate blower operation and reduce energy use. Fure said Delta 3 will send a final report in December and that the village will receive a $5,000 Focus on Energy reimbursement tied to the evaluation.

Fure outlined a likely timeline: the consultant will submit the evaluation in December 2025; a facility plan would be developed in 2026; plans and specifications (and grant applications) in 2027; and construction likely in 2028–29, contingent on funding. The board discussed whether to consider moving village offices to the wastewater site as part of a larger project; Clerk Shawna Atterbury said co-locating staff could be more efficient, though board members raised questions about space and parking.

The board did not take formal action on capital work at the Nov. 3 meeting. Delta 3 will return in February 2026 to discuss priorities and costs for a facility plan and grant strategy.