Commissioners discuss utility coordination for Mammoth South, road‑use agreements and solar ordinance options
Summary
Board members reviewed progress on Mammoth South and other infrastructure projects, asked staff to coordinate road‑use agreements with NIPSCO/AEP through BS Engineering, and heard public concern about solar projects, battery storage and the limits of moratoriums and ordinance changes.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
Pulaski County commissioners discussed coordination with utilities on several infrastructure projects, who pays for road repairs tied to construction, and how the county might approach ordinances on solar, battery storage and data‑center projects.
The meeting reopened a previously paused discussion with BS Engineering about utility projects. Chair (speaker 1) pressed for timelines on Mammoth South and repaving commitments; staff recalled a fall completion for much of the work and noted the company had previously indicated 2026 for road repaving. Participants questioned who would pay for repaving: a staff member asked for clarification whether NIPSCO would cover those costs and the board concluded the county likely bears most of the expense but sought coordination assistance from BS Engineering.
Staff (speaker 2) framed the coordination effort as a communications role: "The primary purpose of this coordination effort is to help facilitate communication between NIPSCO, county departments, emergency services, and the public as work progresses through the county," the staff member said, adding that the team would monitor road closures and provide updates as projects advance.
Commissioners also discussed earlier advice not to change ordinances while Economic Development Agreements (EDAs) were active. Chair (speaker 1) said the county had been advised not to change ordinances at that time but that recommended ordinances for battery storage and data centers had been requested and "might be considered" in the future. Public commenters asked why a previous solar moratorium had been voted down and whether the county could instead impose a cap on commercial solar that could be amended later; commissioners replied that state law allows only a one‑year moratorium on a project and cautioned about using a moratorium without concurrent ordinance work.
No ordinance changes or binding agreements with utilities were approved at this meeting; staff were asked to continue coordination work with BS Engineering and to bring recommended ordinances and timelines back to the board for future consideration.