Hoehne R‑3 board approves $1.36 million GMP for Nunn Construction after initial tie

Hoehne Reorganized School District No. 3 Board of Education · May 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Hoehne Reorganized School District No. 3 Board of Education approved a Guaranteed Maximum Price (GMP) amendment of $1,360,680 for Nunn Construction after an initial 3–3 tie and a subsequent re-vote that passed 4–2. The board also heard the contractor’s presentation and discussed scope and budget concerns.

The Hoehne Reorganized School District No. 3 Board of Education approved a guaranteed maximum price (GMP) amendment with Nunn Construction for a maximum price proposal of $1,360,680 following debate and a re-vote on May 20, 2026.

The board heard a presentation from Kellee Briggs, preconstruction manager, and Kimberly Linan, estimator, of Nunn Construction, who reviewed a narrative and detailed cost estimate outlining the proposed project scope and budget. The presentation began after the representatives arrived at about 7:07 p.m.

Board members raised questions about project costs, scope and budget allocation before voting. The first roll-call on the GMP amendment resulted in a 3–3 tie (Arnhold, Cannon and Monohan voting yes; Blasi, Montoya and Walters voting no), which failed. President Brad Blasi then called for an immediate re-vote; the re-vote passed 4–2 (yes: Todd Arnhold, Jess Cannon, Renee Monohan, Jim Montoya; no: Brad Blasi, Torrey Walters).

The motion was brought by Board Member Todd Arnhold and seconded by Jess Cannon. The minutes record that board members discussed project costs and scope prior to each vote; the record does not quote board members verbatim.

The approved GMP amendment will move the project forward to the next implementation steps identified in the Nunn Construction proposal. The board did not record detailed line-item changes to the budget in the minutes; those specifics are part of the GMP documentation provided by Nunn Construction.

The meeting continued with other routine business and was adjourned at 8:14 p.m.