Council approves paving work not to exceed $600,000 after bid exceeds CIP balance

Old Orchard Beach Town Council · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After reviewing bids that totaled $683,900 for multiple road projects, the council approved paving work with a not-to-exceed cap of $600,000 and discussed alternative paving methods that could lower the overall cost; council asked that work be scheduled after Labor Day.

The Old Orchard Beach Town Council reviewed bids for paving multiple roads and approved the work with an explicit budget cap not to exceed $600,000 after the apparent low bid ($683,900) exceeded the CIP balance.

Public Works staff explained there were three bids; the apparent low bid came in at $683,900 based on an apples-to-apples comparison of road lists and paving methods. The public works director and a councilor said the low bidder also proposed alternate methods (grinding rather than patch-and-overlay) that could reduce the cost to a range closer to $550,000–$575,000. Councilors discussed the discrepancy between the bid and the CIP balance ($600,000) and decided to approve the project with a cap at $600,000 and the flexibility to pursue lower-cost approaches.

A resident, Guy Fontaine, suggested language that the authorization be "not to exceed $600,000" so the council could either use general-fund dollars or return to the council if the project cost exceeded the cap; council adopted that approach. Councilors asked about timing and were told work is expected to start after Labor Day.

The motion to approve the paving with the reduced cap passed 5-0.