Board allows Miller Pipeline to install 6,000-foot distribution line to Brookfield Farms
Summary
The New Castle Utility Board approved Miller Pipeline’s plan to install about 6,000 feet of 2-inch distribution line to serve Brookfield Farms, with tapping locations noted along 20th and Washington; the board voted to permit the work.
Get email alerts on the Pipeline Infrastructure topic
No spam. Unsubscribe anytime.
The New Castle Utility Board voted July 20 to allow Miller Pipeline to install approximately 6,000 feet of 2-inch distribution line to serve the Brookfield Farms subdivision.
A presenter described planned work and said crews will tap the system on the east side of 20th and the south side of Washington, with the trenching and distribution placed primarily within the subdivision. The presenter added that the work is intended to provide distribution capacity to Brookfield Farms rather than individual taps across a broader corridor.
A board member moved to approve the construction; the motion was seconded and carried by voice vote. The board did not record an itemized roll-call tally in the transcript. Staff will coordinate with Miller Pipeline and affected properties on scheduling and traffic control.
The motion authorizes the utility to proceed with permitting and construction coordination for the distribution line.